Tuesday, June 8th - Tuck Pointing Starts on East Side

   


Wednesday, June 9th - Tuck Pointing Continues on West Side

         


Wednesday, June12th - Tuck Pointing Continues on Chimney

   


Wednesday, June18th - Roofing Begins

                                   


Thursday, June19th - Roofing Continues

                           


Monday, June 23rd - Gutters & Downspouts Installed

               


Tuesday, June 24th - Roofing Continues

                                                   